Important Dates in the Lives of Jesus and Mary
which was the beginning of Herod's reign over Jerusalem. In the title of book 15, Josephus writes: BOOK 15
CONTAINING THE INTERVAL OF EIGHTEEN YEARS FROM THE DEATH OF ANTIGONUS TO
THE FINISHING OF THE TEMPLE BY HEROD. Since book 15 covers a period of 18 years, from the
beginning of Herod's reign to the completion of the temple, work on the temple must have been completed
(not begun) in Herod's 18th year.
Also, Josephus places the description of the rebuilding of the Temple at the very end of book 15. If the
rebuilding had begun in Herod's 18th year, then the description of the completion of the rebuilding would fall
into the middle of book 16. But book 16 instead mentions the rebuilding of the Temple in the title of the book
as having already been completed: CONTAINING THE INTERVAL OF TWELVE YEARS FROM THE
FINISHING OF THE TEMPLE BY HEROD TO THE DEATH OF ALEXANDER AND
ARISTOBULUS.
779
Notice from this title that book 16 begins at the time of the completion of the rebuilding
of the Temple. Therefore, the Temple rebuilding did not begin in Herod's 18th year, but rather was completed
in his 18th year.
The statement by Josephus that the rebuilding of the Temple of Jerusalem began in Herod's 15th year
cannot be correct.
780
Josephus describes in detail a famine which took place in Israel during Herod's 13th and
14th years.
781
The year after a two year period of famine is a very unlikely starting point for a major building
project, such as the rebuilding of the Temple of Jerusalem. However, the rebuilding took eight years, so work
on the Temple did occur during Herod's 15th year, and ended in his 18th year.
782
Further confirmation that the rebuilding of the Temple was completed in Herod's 18th year is found in
Josephus' description of another major building project, Cesarea Sebaste. Josephus tells us that Cesarea
Sebaste took nearly ten years to build and was completed in Herod's 28th year.
783
This building project began
nearly 10 years earlier, about the 19th year of Herod's reign. But if Herod had begun to build the temple in his
18th year, he would have had two major building projects going on at the same time. This is highly unlikely,
for Herod had difficulty convincing the Jewish people to participate in even the one major construction
project, to rebuild their own Temple, as Josephus describes: but as he knew the multitude were not ready
nor willing to assist him in so vast a design, he thought to prepare them first by making a speech to them, and
then set about the work itself .
784
On the other hand, if the Temple was completed in Herod's 18th year,
then the extensive resources formerly used to rebuild the Temple could be brought to bear on the Cesarea
Sebaste project. Again, we see that the rebuilding of the Temple of Jerusalem was completed in Herod's 18th
year.
According to Josephus, the rebuilding of the Temple, including the outer enclosures, took 8 years.
785
If the
work was completed in Herod's 18th year, it must have begun 8 years earlier, in Herod's 11th year. The work
on the Temple itself (the Sanctuary where the sacrifices took place) took only 1 years.
786
Josephus notes that
the completion of the rebuilding of the Temple Sanctuary was celebrated with a festival which coincided with
the anniversary of Herod's inauguration as king of Jerusalem.
787
Herod captured Jerusalem in the autumn and
must have been inaugurated as king shortly thereafter, so the rebuilding of the Temple Sanctuary was
completed in the autumn. Therefore, the work on the Temple Sanctuary began in the springtime during
Herod's 11th year, continued for 1 years, and was completed at the end of his 12th year as king of Jerusalem.
Herod captured Jerusalem in autumn of 43
B.C.
, on the fast day (Tishri 10), which fell in mid September
that year.
788
The work on the Temple of Jerusalem began in spring of Herod's 11th year, which would be
spring of 32
B.C.
(Regardless of whether one counts each year of Herod's reign from the autumn at his
inauguration, or from the beginning of the calendar year in January, or from the beginning of the Jewish
sacred calendar in Nisan, the spring of his 11th year would still be 32
B.C.
) The Temple Sanctuary was
completed 1 years later, in autumn of 31
B.C.
And the entire Temple, including the outer enclosures, was
completed about 8 years after the work had begun, in Herod's 18th year, which was 25
B.C.
The Olympiad Years
The modern day Olympics has its origins and inspiration in the ancient Olympic Games held by the
Romans. These Olympic Games were held, as we would count it, every 4 years. The Romans counted it as
every 5th year, since they counted inclusively, that is, they counted the year of the games, plus the 3 following
180
footer
Our partners:
PHP: Hypertext Preprocessor Best Web Hosting
Java Web Hosting
Inexpensive Web Hosting
Jsp Web Hosting
Cheapest Web Hosting
Jsp Hosting
Cheap Hosting
Visionwebhosting.net Business web hosting division of Web
Design Plus. All rights reserved